Please click here >>>> Contact us for more factory prices,shipping and discounts.
Product Description
Fluidized Circulating Bed boiler (as known as FCB boiler) refers to a type of boiler in which polverized fuel is burnt while being blown to circulate in fluidizing motion. FCB boiler is now the most recognizable boiler type, especially in the area of power generation. It is mostly used for burning biomass, kerogen shale and other fuel hard to combust.
FCB boiler has following features:
1. High burning rate: FCB boiler unit, among all the boilers, has the highest buring efficiency (98% to 99%) due to the circulation of fuel propelled by air blown to the furnace.
2. Wide range of choice on fuel: FCB boiler was designed to burning most of fuel that are hard to burn otherwise, such as MSW (Municipal Solid Waste), coal gangue,kerogen shale and animal dung. Wide application of FCB has made power generation available to people in less developed area.
3. Highly developed technology: the application of FCB boiler is one of the most developed area of Chinese power generation generation sector. Technical difficulties such as expansion, overheating, erosion, wearing-out have been overcome over the year, which makes the operation safer than ever.
4. Low maintenance cost & long service: Silicon nitride lining extends the service life to over 20 years and also makes regular maintenance less frequent, compared to other boilers.
5. Easy mounting of heat recovery system: heat recovery system can be mounted to boiler for collecting energy from the exhaust. Combined with Low-temperature steam turbine provided by Runh Power, the FCB boiler is able to generate additional power, for either service power consumption or transmitting to grid.
Runh Power positions itself no only as a supplier of power plant equipment but also an independent contractor of EPC service (engineering, purchase & construction) delivering power station project.
With at least PPA and Feasibility Report in place, Runh Power is able to help the commissioner to secure private investment or loan from the state bank.
-1) Power Purchase Agreement (For independent power producers only)
-2) Feasibility report (In case that there is none, designers and engineers can be dispatched to compile one at the expense of commissioner.)
-3) Sovereign bonds (If sovereign bonds are acquired and the commissioner has 15 % of capital need for the project, Runh Power could start the project while engaging China Export & Credit Insurance Corporation)
-4) Construction Permit (optional)
-5) Fire permit (optional)
-6) Environmental impact assessment (optional)
-7) Land Lease (optional)
-8) Power Generation Power (optional)
-9) Other documents deemed helpful (optional)
Company Profile
Runh Power's rule as a contractor of power plant on EPC basis:
Runh Power is dedicated to provide various kinds of power plant construction on EPC basis, including :
A. conventional power plant (coal-firing, gas-firing, municipal solid waste firing)
B. renewable energy power plant (photovoltaic, photothermal, biomass-firing, hydro power plant)
The scope of work is as follows:
1.The Argumentation of Project
a. Verification of documents submitted
b. Audition of documents by the authority
c. Signing the contract
2. Engineering Design
a. Selection of a complete set of equipment according to the request or Runh Power's recommandation or the request from the commissioner.
b. Design of overall layout and all the sub-systems within the parameter of power plant.
c. Selection of personnel participating in the project
d. Submission of technical solution to the commissioner for review and approval.
3.Equipment Purchase& Transportation
a.Turbo Generator Set and its auxiliary systems (boiler, condensing water collector, deaerator, high pressure and low pressure superheaters, power distribution system. etc )
b. All the construction material, tools, spare parts and other necessities of the project
4. Civil Construction
a. All the civil construction work within the parameter of power plant
5. Operation & Maintenance
a. Operation of power plant (technical counseling) (Optional)
b.Regular maintenance and inspection (Optional)
c.Technical Training Program for Power Plant Personnel (Optional)
d.General Overhaul (Optional)
6. Installation & Testing
a.Installation & testing for all systems & equipment provided by Runh Power
b.Installation, testing & trail run of all systems of a power plant (Optional)
c.Installation, testing & trail run of entire power plant (Optional)
7. Supply of Spare Parts
a. Long-term supply of spare parts and other consumibles.(Optional)
Notice: EPS service, which refers to Engineering, Purchase & Supervision of Construction,is also available at your request, in case you prefer local civil construction contractor to international contractor.
For viewing complete scope of Runh Power's service and more models of boilers, please copy and paste following link to your browser.
Runh Power's service catalog : http://runhpower.en.made-in-china.com
Certifications
References